All Resources Available
The Truman State University, campus infrastructure upgrade project has progressed to a point where the implementation stage of the project is imminent. Stage 1 physical plant improvements are requiring immediate attention, as not to allow for delay in the project. As these diverse efforts proceed, concerns exist that all reasonable measures be taken to assure smooth integration between the Stage 1 physical plant upgrades and the ensuing Stage 2 network equipment implementation project.
ITS campus technical personnel have developed baseline standards along with SBC to be applied to the campus equipment configurations. SBC engineers are ready to begin work with appropriate personnel to implement the network design and appropriate protocols.
The ITS staff has engaged with SBC and Cisco in developing the baseline network design standards is the network project. The version of those standards current as of this date is included herewith as Appendix A; however, it is important to note that the document is subject to possible changes if adjustments are acknowledged.
The standards do incorporate certain strongly definitive characteristics:
The campus network design now suggests certain basic requirements that will be a part of the plan check process. The ITS and Facilities staff members have already recognized those requirements and taken steps to assure that they have been reflected in the attached documents. They are enumerated herein merely as potential check points.
The purpose of the following list is to suggest points of integration where items specified in either Stage 1 or Stage 2 of the TSU build-out on campus might affect the other stage. Local facilities and ITS professionals should make every effort to coordinate their efforts to assure that such requirements are identified and accommodated. The intent is to minimize conflicts and change orders the project.
It has been disclosed an important consideration in regard to the A/C power support required for larger Cisco switches. Due to NTA baseline power redundancy requirements for the Stage 2 network equipment, it is necessary to require that all Cisco Catalyst 65150 series switches be supplied by two 208VAC dedicated circuits, some capable of supporting a 30 ampere load. Further, other Cisco switches expected to be employed in key building telecommunications utility rooms may require two dedicated 20A circuits to meet similar redundancy requirements. Note Table 1 in Appendix A lists the physical design characteristics of most of the network equipment products currently expected to be employed in our campus design.
The above information does not take into account the possible presence of UPS units in the configuration. The proper sockets to support the specific Catalyst power supplies should be planned appropriately. Note Appendix A.
In consideration of the above, the following issues have been addressed:
Will current HVAC designs accommodate the additional heat loads associated with:
SBC will provide patch cables as part of the implementation process, but ITS staff will need to make assurances that those cables are optimally suited to local requirements:
In view of TSU intentions to migrate toward converged networks as proven technology becomes available:
Training has been established for ITS Network staff on Friday afternoons from1:30 to 3:30. The CCNA course curriculum is being implemented at this time. It is further recommended that additional training be made available to staff. Global Knowledge a Cisco certified training partner has been contacted to examine this option.
The following schedule is based on the information provided by SBC that the
crew assigned to do the rack and stack part of the implementation project will
be as follows: One lead engineer (possibly not on-site). One additional second
level engineer, as needed. Two crew members on-site to perform the actual
physical implementation. The following schedule is based on this provided
information, with the recognition that it can be accelerated with additional
crew members. It should be further noted that in discussion with SBC that our
ITS staff's ability to assist in the installation process will be restricted due
to possible warranty default of the equipment. This assistance will be to assist
in the removal of the old equipment, placement of the new equipment for the SBC
crew to install.
Note Appendix E
In summary, the physical requirements must be addressed immediately. Also additional electrical sockets that had not been previously identified as part of the project are to be brought to physical plants attention immediately. Once SBC confirms the space necessary for storage of the equipment in preparation of installation, space needs to be established.